Federal Projects

Louisville Metro Government – Federal/State/Local Program Project Summary

Project:

Broadway & 18th Street

Description:

Align intersection of Broadway and 18th Street by moving the south leg of 18th Street to the east.

KIPDA ID:

1192

State ID:

413.00

Project Mgr.:

John Cosper

Original Prog. Year/Budget:

Utility: FY2007/$40,000
Constr.: FY2008/$160,000

Current Prog. Year/Budget:

ROW: FY2014/$66,000

Constr.: FY2014/$295,000

Anticipated Phase Completion

2016

Anticipated Project Completion

2016

Date of Last Reimbursement:



Outstanding

Balance:



Estimated Backlog:

$361,000

Funding Source:

SLO

Notes:

Comments have been received from SHPO in regards to the archaeological survey and questions are to be addressed in August 2014. Right of way negotiations anticipated Summer 2014.



Project:

Bicycle Parking & Intermodal Transit Facility

Description:

Construction of a new inter-modal transit station at the NW corner of W. Jefferson Street and S. 4th Street

KIPDA ID:

1501

State ID:



Project Mgr.:

Dirk Gowin

Original Prog. Year/Budget:

Design: FY2008/$100,000

Constr.: Future/$900,000

Current Prog. Year/Budget:



Anticipated Phase Completion

NA

Anticipated Project Completion

NA

Date of Last Reimbursement:



Outstanding

Balance:



Estimated Backlog:



Funding Source:

SLO

Notes:

Selected Alternative: No-build



Project:

Cooper Chapel Rd. Section 1

Description:

Phase 1: Reconstruct Cooper Chapel Road from 2 to 3 lanes (3rd lane will be a center turn lane) from KY 61 to Smyrna Parkway. Project length is 1.8 miles.

KIPDA ID:

222

State ID:

403.00

Project Mgr.:

Mache’ Readus-Wright

Original Prog. Year/Budget:

Utility: FY2007/$40,000
Constr.: FY2008/$160,000

Current Prog. Year/Budget:

Constr.: FY2014/$5,720,000

Anticipated Phase Completion

Fall 2015

Anticipated Project Completion

Fall 2015

Date of Last Reimbursement:



Outstanding

Balance:



Estimated Backlog:



Funding Source:

SLO

Notes:

Construction began August 4 2014 (18 month construction period) Public meeting held July 31 2014






Project:

Cooper Chapel Rd. Section 3

Description:

Extend and construct 2 lane roadway with a continuous center-turn lane from KY 864 (Beulah Church Road) to US 31E (Bardstown Road) at Bardstown Falls Road. Project will incorporate sidewalks and 10' paved shoulders.

KIPDA ID:

223

State ID:

404.01

Project Mgr.:

Mache’ Readus-Wright

Original Prog. Year/Budget:

ROW: FY2011/$4,000,000

Current Prog. Year/Budget:

ROW: FY2014/$4,293,550

Anticipated Phase Completion



Anticipated Project Completion



Date of Last Reimbursement:



Outstanding

Balance:



Estimated Backlog:

$4,293,550

Funding Source:

SLO

Notes:

Phase 1 design complete. Requested additional design funding for Phase 2 design.




Project:

English Station Rd.

Description:

Widen English Station Road from 2 to 3 lanes (3rd lane will be a center turn lane) from Aiken Road to Avoca Road.

KIPDA ID:

188

State ID:

353.00

Project Mgr.:

John Cosper

Original Prog. Year/Budget:

Design: FY2009/$200,000

ROW: FY2010/$2,000,000

Utility: FY2011/$200,000

Constr.: FY2012/$2,500,000

Current Prog. Year/Budget:

ROW: Authorized

Utility: Authorized

Constr.: FY2015/$3,093,376

Anticipated Phase Completion



Anticipated Project Completion



Date of Last Reimbursement:



Outstanding

Balance:



Estimated Backlog:

$3,093,376

Funding Source:

SLO

Notes:

KYTC has taken over sponsorship and project management.



Project:

Hill Street Sidewalk Rehabilitation

Description:

Rehabilitation of sidewalks on Hill Street between 6th St. and 7th St.

KIPDA ID:

2104

State ID:



Project Mgr.:

Dirk Gowin

Original Prog. Year/Budget:

Design: FY2014/$60,000

Constr.: FY2014/$240,000

Current Prog. Year/Budget:

Design: FY2014/$60,000

Constr.: FY2014/$240,000

Anticipated Phase Completion

Fall 2014

Anticipated Project Completion

Summer 2015

Date of Last Reimbursement:



Outstanding

Balance:



Estimated Backlog:

$240,000

Funding Source:

SLO

Notes:

Initiating design under URS statewide contract




Project:

Hubbards Lane

Description:

Widen Hubbards Lane from 2 to 3 lanes (3rd lane will be a center turn lane) from US 60 (Shelbyville Road) to KY 1447 (Westport Road). Add bike lanes to Hubbards Lane from Kresge Way to KY 1447. Project length is 0.6 mi.

KIPDA ID:

384

State ID:



Project Mgr.:

Al Andrews

Original Prog. Year/Budget:

Design: FY2010/$300,000

Utility: Future

Constr.: Future

Current Prog. Year/Budget:

Design: FY2012/$343,200 (Authorized)

Utility: FY2016/$500,000

Constr.: FY2016/$2,000,000

Anticipated Phase Completion



Anticipated Project Completion



Date of Last Reimbursement:



Outstanding

Balance:



Estimated Backlog:

$---

Funding Source:

SLO

Notes:

Under design/ Setting up second stakeholders’ meeting.



Project:

I-65

Description:

Extend and reconstruct I-65 southbound ramp to Brook Street and Floyd Street.

KIPDA ID:

224

State ID:

378.10

Project Mgr.:

Dirk Gowin

Original Prog. Year/Budget:

Design: FY2008/$250,000

Constr.: FY2009/$3,750,000

Current Prog. Year/Budget:

Design: FY2014/750,000

Utility: FY2015/$750,000

Constr.: FY2015/$1,500,000

Anticipated Phase Completion

Design Fall 2014

Anticipated Project Completion

2016

Date of Last Reimbursement:



Outstanding

Balance:



Estimated Backlog:

$4,750,000

Funding Source:

SLO

Notes:

Toll credit request approved. MOA being routed for signatures.



Project:

One-Way Street Conversion to Two-Way Phase 1

Description:

Conversion of one-way streets in downtown Louisville to two-way traffic (Main, Jefferson, Liberty, Muhammad Ali, Chestnut, 3rd Streets, 8th, 7th, Shelby, Campbell Streets).

KIPDA ID:

1809

State ID:



Project Mgr.:

Dirk Gowin

Pat Johnson

Original Prog. Year/Budget:

Design: FY2010/$180,000

Constr.: FY2010/$1,905,200

Current Prog. Year/Budget:

Design: FY2011/$225,000 (Authorized)

Constr.: FY2014/$2,381,500

Anticipated Phase Completion

Design Fall 2014

Anticipated Project Completion

Fall 2015

Date of Last Reimbursement:



Outstanding

Balance:



Estimated Backlog:

$2,606,500

Funding Source:

SLO

Notes:

Revised TIP description to separate Metro roadways from State roadways. Requires TIP amendment anticipated October 2014






Project:

One-Way Street Conversion to Two-Way Phase 2

Description:

Conversion of one-way streets in downtown Louisville to two-way traffic (Main, 3rd, 8th, 7th, Shelby, Campbell Streets).

KIPDA ID:

1810

State ID:



Project Mgr.:

Dirk Gowin

Pat Johnson

Original Prog. Year/Budget:

Constr.: FY2011/$748,000

Current Prog. Year/Budget:

Constr.: FY2014/$748,000

Anticipated Phase Completion

2017

Anticipated Project Completion

2017

Date of Last Reimbursement:



Outstanding

Balance:



Estimated Backlog:

$748,000

Funding Source:

SLO

Notes:

On hold for the bridges project.



Project:

River Road

Description:

Widen from 2 to 4 lanes from Beargrass Creek to Zorn Ave.

KIPDA ID:

163

State ID:

91.02

Project Mgr.:

John Cosper

Original Prog. Year/Budget:

ROW: FY2008/$550,000

Utility: FY2008/$1,190,000

Constr.: FY2009/$5,000,000

Current Prog. Year/Budget:

ROW: FY2012/$4,000,000 (Authorized)

Utility: FY2013/$3,000,000 (Authorized)

Constr.: FY2014/$11,000,000

Anticipated Phase Completion

2015

Anticipated Project Completion

2018

Date of Last Reimbursement:



Outstanding

Balance:



Estimated Backlog:

$14,000,000

Funding Source:

SLO

Notes:

ROW acquisition nearly complete; agreement to be developed with River Metals Recycling regarding use of Metro property as a driveway. Currently negotiating utility agreements. Utility design in progress for gas and electric; other utilities to follow. MSD and LWC design included in roadway plans. Construction anticipated 2016.



Project:

Seneca Loop Extensions, East and West

Description:

East: Design and construction completing the loop in Seneca Park by adding bicycle facilities on Cannons Ln, Dutchman's Ln and Taylorsville Rd.; West: Design and construction …

KIPDA ID:

1192

State ID:

413.00

Project Mgr.:

Mojgan Taghizadeh

Original Prog. Year/Budget:

Constr.: FY2007/$245,000

Constr.: FY2008/$500,000

Constr.: FY2010/$220,000

Current Prog. Year/Budget:

Constr.: FY2009/$245,000 (Authorized)

Constr.: FY2013/$770,000 (Authorized)

Anticipated Phase Completion

August 2014

Anticipated Project Completion

August 2014

Date of Last Reimbursement:



Outstanding

Balance:



Estimated Backlog:

$770,000

Funding Source:

SLO

Notes:

Construction is currently under way. Right of Entry agreement between Metro and LRAA is fully executed, project on schedule.






Project:

Bicycle & Pedestrian Striping, Signage & Signalization

Description:

Provide striping and signage for Louisville Metro's expanding bicycle and pedestrian facilities to enhance the safety of the roadways for bicyclists and pedestrians.

KIPDA ID:

1786

State ID:



Project Mgr.:

Rolf Eisinger

Original Prog. Year/Budget:

Design: FY2011/$35,000

Constr.: FY2011/$134,000

Current Prog. Year/Budget:

Design: FY2014/$35,000

Constr.: FY2015/$134,000

Anticipated Phase Completion



Anticipated Project Completion



Date of Last Reimbursement:



Outstanding

Balance:



Total Award:

$134,000

Funding Source:

TE

Notes:

Waiting for MOA from KYTC.

Project:

Bike/Ped Prog. 2010 (Bike Sharing Business Plan)

Description:

Funds will be used to procure a firm to assess the feasibility of a bike sharing station Prog. in Louisville and to create a business plan for the Prog..

KYTC Contract Number:

PO2-628-1300006097

State ID:



Project Mgr.:

Rolf Eisinger

Original Prog. Year/Budget:

Planning: FY2011/$100,000

Current Prog. Year/Budget:

Planning.: FY2014/$100,000

Anticipated Phase Completion



Anticipated Project Completion



Date of Last Reimbursement:



Outstanding

Balance:



Total Award:

$100,000

Funding Source:

CMAQ

Notes:

Currently underway. Finalizing business plan.

Project:

LaGrange Road Bike/Ped Project

Description:

Design, ROW acquisition, utility relocation, and construction of bike lanes and a sidewalk along LaGrange Road from Lakeland to Lyndon Lane.

KYTC Contract Number:

PO2-628-0900022388 (old)

PO2-628-130006422 (New)

State ID:



Project Mgr.:

Dirk Gowin

Original Prog. Year/Budget:

Planning: FY2009/$828,000

Current Prog. Year/Budget:

Design.: FY2013/$207,000

Anticipated Phase Completion

Design: Fall 2014

Anticipated Project Completion

2015

Date of Last Reimbursement:



Outstanding

Balance:



Total Award:

$828,000

Funding Source:

CMAQ

Notes:

Requires decision by OLP to expand Phase 1 activities. Request by email 10/14/13. No response as of 8/4/14




Project:

LaGrange Road Pedestrian Facility

Description:

Construct sidewalks, bike lanes and intersection improvements along LaGrange Road and KY 146.

KYTC Contract Number:

PO2-628-1100005479

State ID:



Project Mgr.:

Dirk Gowin

Original Prog. Year/Budget:

Design: FY2013/$77,600

Current Prog. Year/Budget:

Design.: FY2013/$77,600

Original Auth.Date:

4/12/2011



Anticipated Phase Completion

Fall 2014

Anticipated Project Completion

Fall 2015

Date of Last Reimbursement:



Outstanding

Balance:



Total Award:

$1,356,400

Funding Source:

TE

Notes:

Requires decision by OLP to expand Phase 1 activities. Request by email 10/14/13. No response as of 8/4/14



Project:

Louisville Metro Strategic Multimodal Transportation Plan (Move Louisville)

Description:

Development of the Louisville Strategic Multimodal Transportation Plan that is a community based plan that provides policy guidance to integrate and balance traditional and multi-modal transportation facilities with both existing and desired land use patterns, supporting sustainable development and

improved quality of life.

KIPDA ID:

2050

State ID:



Project Mgr.:

Dirk Gowin

Patti Clare

Original Prog. Year/Budget:

Planning: FY2012/$600,000

Current Prog. Year/Budget:

Planning: FY2013/$600,000

Anticipated Phase Completion

Fall 2014

Anticipated Project Completion

Fall 2014

Date of Last Reimbursement:



Outstanding

Balance:



Total Award:

$600,000

Funding Source:

TCSP

Notes:

Planning underway, will provide guidance to Metro for next 25 years.

Project:

Portland Elementary

Description:

Provide sidewalks, ADA ramps, signage and striping with the Portland historic district.

KYTC Contract Number:

PO2-628-100002638

State ID:



Project Mgr.:

Mojgan Taghizadeh

Original Prog. Year/Budget:

Constr.: FY2011/$45,465

Current Prog. Year/Budget:

Constr.: FY2014/$45,465

Anticipated Phase Completion

Fall 2014 (anticipated)

Anticipated Project Completion

Fall 2014 (anticipated)

Date of Last Reimbursement:



Outstanding

Balance:



Total Award:

$45,465

Funding Source:

SRTS

Notes:

Retaining wall design is complete. Awaiting NTP from OLP.




Project:

Metro-Wide Traffic Signals

Description:

Metro-wide traffic signal synchronization Phase I.

KYTC Contract Number:

PO2-628-1100002958

State ID:



Project Mgr.:

Pat Johnson

Original Prog. Year/Budget:

Planning: FY2011/$828,000

Current Prog. Year/Budget:

ROW: FY2014/$66,000

Constr.: FY2014/$295,000

Anticipated Phase Completion



Anticipated Project Completion



Date of Last Reimbursement:



Outstanding

Balance:



Total Award:

$800,000

Funding Source:

CMAQ

Notes:

Suburban ATMS Communications Pilot Project Underway and On-going. RFQ’s being developed for a New Systems Manager Contract and Critical Corridor(s) Traffic Signal Retiming

Project:

Walkable Communities II (Fern Valley Road)

Description:

Sidewalks, crosswalks, pedestrian crossing signals, signage, universal access features, and other infrastructure improvements.

KYTC Contract Number:

PO2-628-0900022390 (old)

PO2-628-1300006410 (new)

State ID:



Project Mgr.:

Dirk Gowin

Original Prog. Year/Budget:

Design/Construction:

FY2009/$300,000

Current Prog. Year/Budget:

Constr.: FY2014/$240,000

Anticipated Phase Completion

Fall 2014

Anticipated Project Completion

Fall 2014

Date of Last Reimbursement:



Outstanding

Balance:



Total Award:

$300,000

Funding Source:

CMAQ

Notes:

Awaiting MOA for construction.

Project:

Buechel Streetscape Phase I

Description:

New sidewalks, curbing, ADA ramps, landscaping,, drainage and other ancillary improvements from Buechel Bypass to Six Mile Lane.

KYTC Contract Number:

Metro Funding

State ID:



Project Mgr.:

John Cosper

Original Prog. Year/Budget:

2012

600,000

Current Prog. Year/Budget:

Constr.: FY2014

$567,000

Anticipated Phase Completion

June 2014

Anticipated Project Completion

June 2014

Date of Last Reimbursement:



n/a

Outstanding

Balance:



n/a

Total Award:

$567,000

Funding Source:

Metro Council

Notes:

Construction complete; landscaping to be completed October 2014.


Project:

Buechel Streetscape Phase II

Description:

New sidewalks, curbing, ADA ramps, landscaping,, drainage and other ancillary improvements from Six Mile Lane. West to Buechel Bypass

KYTC Contract Number:

5-8702

State ID:



Project Mgr.:

Mojgan Taghizadeh

Original Prog. Year/Budget:

2013

45000 Design

270,000 Construction

Current Prog. Year/Budget:

2013

45000 Design

270,000 Construction

Anticipated Phase Completion

Summer 2014

Anticipated Project Completion

Fall 2014

Date of Last Reimbursement:



n/a

Outstanding

Balance:



n/a

Total Award:

pending

Funding Source:

KYTC

Notes:

Negotiations underway with design consultant. MOA request for construction delayed until design is complete.

Project:

Buechel Bank Road Widening

Description:

Widen and improve Buechel Bank Road from Buechel Bypass to the GE Entrance Road

KYTC Contract Number:

5-8105.00



State ID:



Project Mgr.:



Original Prog. Year/Budget:

Design/Construction:



Current Prog. Year/Budget:



Anticipated Phase Completion

R/W Summer 2014

Utilities Fall 3014 to Summer 2015

Construction Summer 2015 to Summer 2016

Anticipated Project Completion

Summer 2016

Date of Last Reimbursement:



Outstanding

Balance:



Total Award:



Funding Source:



Notes:

MOA for utilities requested June 9, 2014. Additional information requested by KYTC July 2014.

Project:

KY 22

Description:



KYTC Contract Number:



State ID:



Project Mgr.:

Mache’ Readus-Wright

Original Prog. Year/Budget:

Design/Construction:



Current Prog. Year/Budget:



Anticipated Phase Completion



Anticipated Project Completion



Date of Last Reimbursement:



Outstanding

Balance:



Total Award:



Funding Source:



Notes:

Project is complete – awaiting final reimbursement.


Project:

Meyzeek Middle School

Description:

SRTS project

KYTC Contract Number:



State ID:



Project Mgr.:

Mache’ Readus-Wright

Original Prog. Year/Budget:

Design/Construction:

170,000 Federal

Current Prog. Year/Budget:



Anticipated Phase Completion

Fall 2014

Anticipated Project Completion

Fall 2014

Date of Last Reimbursement:



Outstanding

Balance:



Total Award:



Funding Source:



Notes:

Project has been bid twice with bids coming in over budget. Project is being re-designed to reduce scope. Historic Preservation officer now requiring limestone curbing in lieu of concrete. This will further complicate the redesign/budget problem.

Principal has approved redesign.

KYTC encroachment permit application to be updated.

Safety video has been completed.

Project:

E Market Street (US-31E) Project

Description:

Improve mobility & safety for various modes of transportation while transforming the area into an attractive urban space.

KIPDA ID:

2064

State ID:

056 031E 016-018

05-08703

Project Mgr.:

Jeff Brown

Original Prog. Year/Budget:

Design: FY2013/$1,350,000
Construction: FY2015/$8,500,000

Current Prog. Year/Budget:



Anticipated Phase Completion

Schematic Design July 2014

CDs & Letting December 2014

Anticipated Project Completion

Fall 2016

Date of Last Reimbursement:



Outstanding

Balance:



Estimated Backlog:



Funding Source:

SPP

Notes:

We are getting ready to move into the Construction Design phase of the project and will be meeting with KTC and the consultant in the next week or two to review the scope of work the consultant has proposed. KTC has approved the schematic design


Project:

Dixie Highway at I-264

Description:

Improve mobility & safety for various modes of transportation while transforming the area into an attractive urban space.

KIPDA ID:

State ID:

Project Mgr.:

Al Andrews

Original Prog. Year/Budget:

Current Prog. Year/Budget:



Anticipated Phase Completion

Anticipated Project Completion

Date of Last Reimbursement:



Outstanding

Balance:



Estimated Backlog:



Funding Source:

Notes:

Phase I design under way including utilities, landscaping and lighting. Coordinating with FHWA on pedestrian issues at I-264.





Project:

West Extension of River Road

Description:

Extend River Road west of current terminus in downtown Louisville

KIPDA ID:

State ID:

Project Mgr.:

Dirk Gowin/Patti Clare

Original Prog. Year/Budget:

Current Prog. Year/Budget:



Anticipated Phase Completion

Anticipated Project Completion

Date of Last Reimbursement:



Outstanding

Balance:



Estimated Backlog:



Funding Source:

TCSP

Notes:

Determining funding source for local match.